Budgets and burn

Hours logged against each project's budget, with the forecast at the end date.

Over budget

2

243.3 h over in total

At risk

1

Forecast above budget

Active projects

7

16 people logging

Billable

70%

Last 12 weeks

Budget vs logged
Forecast: logged hours plus the last four weeks' average until the end date.
  • Budget
  • Logged
  • Forecast
Swiss Post · ends 27 Nov 2026
Over budget
115%

1,532 of 1,330 h

202 h over budget

Forecast 1,920 h · 96.9 h/week

SP
NV
SV
HR
Details
Migros · ends 20 Nov 2026
Over budget
104%

1,011.3 of 970 h

41.3 h over budget

Forecast 1,203 h · 63.8 h/week

JM
HR
GR
TW
Details
Banque Léman · ends 18 Dec 2026
At risk
76%

1,579.5 of 2,090 h

510.5 h left

Forecast 2,288 h · 101.3 h/week

JI
TK
JZ
RB
Details
Helvetia Rail · ends 15 Jan 2027
On track
54%

1,251 of 2,330 h

1,079 h left

Forecast 2,097 h · 76.9 h/week

GR
RB
JI
FC
Details
Alpiq · ends 12 Feb 2027
On track
42%

1,303.8 of 3,070 h

1,766.3 h left

Forecast 2,605 h · 86.8 h/week

XC
DG
TK
JM
Details
Internal · ends 26 Mar 2027
On track
41%

929.5 of 2,240 h

1,310.5 h left

Forecast 2,120 h · 56.7 h/week

NV
JF
SV
SP
Details
Internal · ends 5 Nov 2027
On track
21%

1,972.5 of 9,490 h

7,517.5 h left

Forecast 8,535 h · 123.8 h/week

JG
TW
FC
JF
Details